Commissioning

Pre-Commissioning:Picture10

  • Solo run and run test for pump, air compressor, fan, air blowing
  • Start oil flushing and water flushing for utility system
  • Start up condensate system, HP, LP BFWP
  • Start blue oil system of steam turbine for flushing and run test trip block system, steam control valve, stop valve over speed mechanical trip
  • Steam blowing
  • Frist steam to steam turbine

 

Commissioning:Picture9

  • Start up sea water system, closed cooling water, chemical system
  • Blue oil, hydraulic oil…
  • Run test for pump, air compressor, fan
  • Correct flow rate, pressure, temperature value for operation
  • Short circuit test, earth test, synchronizing, energization load test, load reject test