Commissioning

Pre-Commissioning:

  • Solo run and run test for the pump, air compressor, fan, air blowing
  • Start oil flushing and water flushing for utility system
  • Startup condensate system, HP, LP BFWP
  • Start blue oil system of steam turbine for flushing and run test trip block system, steam control valve, stop valve over speed mechanical trip
  • Steam blowing
  • Frist steam to steam turbine

Commissioning:

  • Startup seawater system, closed cooling water, chemical system
  • Blue oil, hydraulic oil…
  • Run test for the pump, air compressor, fan
  • Correct flow rate, pressure, temperature value for operation
  • Short circuit test, earth test, synchronizing, energization load test, load reject test

 

 