การตรวจสอบและซ่อมแซมท่อก๊าซเชื้อเพลิง

ข้อมูลเชิงลึกอ้างอิง

ข้อมูลโครงการ

ที่ตั้ง

เวียดนาม

ปี

2023

ขอบเขตงาน

  • Based on the survey, determining the supports can be conducted either online or offline. For offline conditions, there are 113 points estimated to take around 10 days. If necessary, a Hand Cutting Machine will be used to cut the support.
  • For online conditions, there are 142 points estimated to be completed at a rate of 2 points per day. Ringlock scaffolding will be erected for easy access to the workplace.
  • Using Ringlock scaffolding to work at heights.
  • Reinforced BS1139 scaffolding used to support gas pipelines.
  • Removing pipe supports to gain access to corrosion points.
  • Utilizing high-pressure water cleaning at 300-350 bar to remove debris and contaminants.
  • Implementing measures to protect the work area and prevent dust and other forms of contamination from affecting nearby equipment.
  • Applying slurry blast cleaning on the corrosion points to minimize sparks.
  • Conducting Ultrasonic Tests to assess pipe thickness and generate a comprehensive report.
  • For thickness loss, we use Belzona 1161 (Super UnderWater-Meta), a two-part composite material with a surface-tolerant epoxy resin and silicon steel alloy, to restore the original thickness.

รายละเอียดเพิ่มเติมเกี่ยวกับ การตรวจสอบและซ่อมแซมท่อก๊าซเชื้อเพลิง

คำอธิบายการทำงาน

  • Based on the survey, determining the supports can be conducted either online or offline. For offline conditions, there are 113 points estimated to take around 10 days. If necessary, a Hand Cutting Machine will be used to cut the support.
  • For online conditions, there are 142 points estimated to be completed at a rate of 2 points per day. Ringlock scaffolding will be erected for easy access to the workplace.
  • Using Ringlock scaffolding to work at heights.
  • Reinforced BS1139 scaffolding used to support gas pipelines.
  • Removing pipe supports to gain access to corrosion points.
  • Utilizing high-pressure water cleaning at 300-350 bar to remove debris and contaminants.
  • Implementing measures to protect the work area and prevent dust and other forms of contamination from affecting nearby equipment.
  • Applying slurry blast cleaning on the corrosion points to minimize sparks.
  • Conducting Ultrasonic Tests to assess pipe thickness and generate a comprehensive report.
  • For thickness loss, we use Belzona 1161 (Super UnderWater-Meta), a two-part composite material with a surface-tolerant epoxy resin and silicon steel alloy, to restore the original thickness.

ความแข็งแกร่ง

  • Ensuring compliance with international standards for quality and safety.
  • A team of highly experienced staff.
  • Ringlock scaffolding is easier to transport, assemble, and dismantle compared to conventional scaffolding systems.

ข้อมูลอ้างอิง

โครงการที่เกี่ยวข้อง

Blasting and Painting for Purus Kingpost Item

ที่ตั้ง:

เวียดนาม

ปี:

2025

อุตสาหกรรม:

น้ำมันก๊าซ

Belzona application for impeller of centrifugal pump

ที่ตั้ง:

เวียดนาม

ปี:

2025

อุตสาหกรรม:

น้ำมันก๊าซ

โซลูชันการป้องกันที่ครอบคลุมสำหรับแพลตฟอร์มนอกชายฝั่งที่ไม่มีคนควบคุม

ที่ตั้ง:

ประเทศไทย

ปี:

2024

อุตสาหกรรม:

ปลายน้ำ, น้ำมันก๊าซ

สิ่งที่เรานำเสนอ

อุตสาหกรรม

จากบล็อก

ข่าวล่าสุด

การตอบรับของลูกค้า

จดหมายรับรอง