คำอธิบายการทำงาน
- Demolishing all pipelines, machinery bases, and electrical junction boxes connected to the generator.
- Drilling 24 holes with a diameter of Ø52 on steel plates.
- Drilling 24 holes with a diameter of Ø46 on the concrete foundation.
- Removing 2 indoor air conditioning units.
- Cleaning the drilled holes and installing anchor bolts using Hilti chemical agents.
- Cleaning and polishing the surfaces.
- Performing plastering work.
- Replacing 12 internal M36 washing machines.
- Reinstalling 2 cooling systems and all associated pipelines, platforms, etc.
- Conducting inspections, cleaning, and handing over the project.