Kiểm tra và sửa chữa đường ống Gas Gas

Thông tin tham khảo

Thông tin dự án

Địa điểm

Việt Nam

Năm

2023

Phạm vi công việc

  • Based on the survey, determining the supports can be conducted either online or offline. For offline conditions, there are 113 points estimated to take around 10 days. If necessary, a Hand Cutting Machine will be used to cut the support.
  • For online conditions, there are 142 points estimated to be completed at a rate of 2 points per day. Ringlock scaffolding will be erected for easy access to the workplace.
  • Using Ringlock scaffolding to work at heights.
  • Reinforced BS1139 scaffolding used to support gas pipelines.
  • Removing pipe supports to gain access to corrosion points.
  • Utilizing high-pressure water cleaning at 300-350 bar to remove debris and contaminants.
  • Implementing measures to protect the work area and prevent dust and other forms of contamination from affecting nearby equipment.
  • Applying slurry blast cleaning on the corrosion points to minimize sparks.
  • Conducting Ultrasonic Tests to assess pipe thickness and generate a comprehensive report.
  • For thickness loss, we use Belzona 1161 (Super UnderWater-Meta), a two-part composite material with a surface-tolerant epoxy resin and silicon steel alloy, to restore the original thickness.

Chi tiết bổ sung về Kiểm tra và sửa chữa đường ống Gas Gas

Mô tả công việc

  • Based on the survey, determining the supports can be conducted either online or offline. For offline conditions, there are 113 points estimated to take around 10 days. If necessary, a Hand Cutting Machine will be used to cut the support.
  • For online conditions, there are 142 points estimated to be completed at a rate of 2 points per day. Ringlock scaffolding will be erected for easy access to the workplace.
  • Using Ringlock scaffolding to work at heights.
  • Reinforced BS1139 scaffolding used to support gas pipelines.
  • Removing pipe supports to gain access to corrosion points.
  • Utilizing high-pressure water cleaning at 300-350 bar to remove debris and contaminants.
  • Implementing measures to protect the work area and prevent dust and other forms of contamination from affecting nearby equipment.
  • Applying slurry blast cleaning on the corrosion points to minimize sparks.
  • Conducting Ultrasonic Tests to assess pipe thickness and generate a comprehensive report.
  • For thickness loss, we use Belzona 1161 (Super UnderWater-Meta), a two-part composite material with a surface-tolerant epoxy resin and silicon steel alloy, to restore the original thickness.

Sức mạnh

  • Ensuring compliance with international standards for quality and safety.
  • A team of highly experienced staff.
  • Ringlock scaffolding is easier to transport, assemble, and dismantle compared to conventional scaffolding systems.

DỰ ÁN

Các dự án liên quan

Phun cát và sơn phủ bảo vệ cho hạng mục Purus Kingpost

Vị trí:

Việt Nam

Năm:

2025

Các ngành nghề:

Dầu khí

Belzona application for impeller of centrifugal pump

Vị trí:

Việt Nam

Năm:

2025

Các ngành nghề:

Dầu khí

Dịch vụ phun phủ bảo vệ toàn diện giàn khoan trên biển không người

Vị trí:

Thái Lan

Năm:

2024

Các ngành nghề:

Công nghiệp dầu khí (Hạ Nguồn), Dầu khí

Những gì chúng tôi đang cung cấp

Lĩnh vực

BLOG

Tin tức mới nhất

PHẢN HỒI CỦA KHÁCH HÀNG

Thư cảm ơn